library

Applying Last Planner in the Nigerian Construction Industry

Applying Last Planner in the Nigerian Construction Industry

The Nigerian construction industry has yet to adapt Lean Construction modern to eliminate or minimize waste and improve value. This makes shelter unaffordable to low-income citizens. This paper reports on and evaluates the effectiveness of implementing the Last Planner® System (LPS) in Nigeria by comparing it with the traditional method on construction of 300 housing units by the Yobe State Government of Nigeria in Damaturu. The effectiveness of LPS was measured in terms of time to complete 50 houses AND performance criteria. LPS proved superior even though most of the party’s involve were not familiar with it. Wider interest in applying LPS and Lean Construction in Yobe State has developed in the top management staff of the Ministry of Housing. It was concluded that effective training and implementation in the application of Lean Construction techniques will reduce waste and non-value-adding steps from planning and design through construction.This will increase value and reduce the exorbitant cost and time to deliver structures.

library

Applying Last Planner in the Nigerian Construction Industry

Applying Last Planner in the Nigerian Construction Industry

The Nigerian construction industry has yet to adapt Lean Construction modern to eliminate or minimize waste and improve value. This makes shelter unaffordable to low-income citizens. This paper reports on and evaluates the effectiveness of implementing the Last Planner® System (LPS) in Nigeria by comparing it with the traditional method on construction of 300 housing units by the Yobe State Government of Nigeria in Damaturu. The effectiveness of LPS was measured in terms of time to complete 50 houses AND performance criteria. LPS proved superior even though most of the party’s involve were not familiar with it. Wider interest in applying LPS and Lean Construction in Yobe State has developed in the top management staff of the Ministry of Housing. It was concluded that effective training and implementation in the application of Lean Construction techniques will reduce waste and non-value-adding steps from planning and design through construction.This will increase value and reduce the exorbitant cost and time to deliver structures.

Applying Last Planner in the Nigerian Construction Industry

Applying Last Planner in the Nigerian Construction Industry

The Nigerian construction industry has yet to adapt Lean Construction modern to eliminate or minimize waste and improve value. This makes shelter unaffordable to low-income citizens. This paper reports on and evaluates the effectiveness of implementing the Last Planner® System (LPS) in Nigeria by comparing it with the traditional method on construction of 300 housing units by the Yobe State Government of Nigeria in Damaturu. The effectiveness of LPS was measured in terms of time to complete 50 houses AND performance criteria. LPS proved superior even though most of the party’s involve were not familiar with it. Wider interest in applying LPS and Lean Construction in Yobe State has developed in the top management staff of the Ministry of Housing. It was concluded that effective training and implementation in the application of Lean Construction techniques will reduce waste and non-value-adding steps from planning and design through construction.This will increase value and reduce the exorbitant cost and time to deliver structures.

Applying Last Planner in the Nigerian Construction Industry

Applying Last Planner in the Nigerian Construction Industry

The Nigerian construction industry has yet to adapt Lean Construction modern to eliminate or minimize waste and improve value. This makes shelter unaffordable to low-income citizens. This paper reports on and evaluates the effectiveness of implementing the Last Planner® System (LPS) in Nigeria by comparing it with the traditional method on construction of 300 housing units by the Yobe State Government of Nigeria in Damaturu. The effectiveness of LPS was measured in terms of time to complete 50 houses AND performance criteria. LPS proved superior even though most of the party’s involve were not familiar with it. Wider interest in applying LPS and Lean Construction in Yobe State has developed in the top management staff of the Ministry of Housing. It was concluded that effective training and implementation in the application of Lean Construction techniques will reduce waste and non-value-adding steps from planning and design through construction.This will increase value and reduce the exorbitant cost and time to deliver structures.

Applying Last Planner in the Nigerian Construction Industry

This paper discusses the implementation and challenges of applying the Last Planner System in the Nigerian construction context.

Applying Last Planner in the Nigerian Construction Industry

The Nigerian construction industry has yet to adapt Lean Construction modern to eliminate or minimize waste and improve value. This makes shelter unaffordable to low-income citizens. This paper reports on and evaluates the effectiveness of implementing the Last Planner® System (LPS) in Nigeria by comparing it with the traditional method on construction of 300 housing units by the Yobe State Government of Nigeria in Damaturu. The effectiveness of LPS was measured in terms of time to complete 50 houses AND performance criteria. LPS proved superior even though most of the party’s involve were not familiar with it. Wider interest in applying LPS and Lean Construction in Yobe State has developed in the top management staff of the Ministry of Housing. It was concluded that effective training and implementation in the application of Lean Construction techniques will reduce waste and non-value-adding steps from planning and design through construction.This will increase value and reduce the exorbitant cost and time to deliver structures.

Applying Last Planner in the Nigerian Construction Industry

Applying Last Planner in the Nigerian Construction Industry

The Nigerian construction industry has yet to adapt Lean Construction modern to eliminate or minimize waste and improve value. This makes shelter unaffordable to low-income citizens. This paper reports on and evaluates the effectiveness of implementing the Last Planner® System (LPS) in Nigeria by comparing it with the traditional method on construction of 300 housing units by the Yobe State Government of Nigeria in Damaturu. The effectiveness of LPS was measured in terms of time to complete 50 houses AND performance criteria. LPS proved superior even though most of the party’s involve were not familiar with it. Wider interest in applying LPS and Lean Construction in Yobe State has developed in the top management staff of the Ministry of Housing. It was concluded that effective training and implementation in the application of Lean Construction techniques will reduce waste and non-value-adding steps from planning and design through construction.This will increase value and reduce the exorbitant cost and time to deliver structures.

Applying Last Planner in the Nigerian Construction Industry

Applying Last Planner in the Nigerian Construction Industry

The Nigerian construction industry has yet to adapt Lean Construction modern to eliminate or minimize waste and improve value. This makes shelter unaffordable to low-income citizens. This paper reports on and evaluates the effectiveness of implementing the Last Planner® System (LPS) in Nigeria by comparing it with the traditional method on construction of 300 housing units by the Yobe State Government of Nigeria in Damaturu. The effectiveness of LPS was measured in terms of time to complete 50 houses AND performance criteria. LPS proved superior even though most of the party’s involve were not familiar with it. Wider interest in applying LPS and Lean Construction in Yobe State has developed in the top management staff of the Ministry of Housing. It was concluded that effective training and implementation in the application of Lean Construction techniques will reduce waste and non-value-adding steps from planning and design through construction.This will increase value and reduce the exorbitant cost and time to deliver structures.

Applying Last Planner in the Nigerian Construction Industry

Applying Last Planner in the Nigerian Construction Industry

The Nigerian construction industry has yet to adapt Lean Construction modern to eliminate or minimize waste and improve value. This makes shelter unaffordable to low-income citizens. This paper reports on and evaluates the effectiveness of implementing the Last Planner® System (LPS) in Nigeria by comparing it with the traditional method on construction of 300 housing units by the Yobe State Government of Nigeria in Damaturu. The effectiveness of LPS was measured in terms of time to complete 50 houses AND performance criteria. LPS proved superior even though most of the party’s involve were not familiar with it. Wider interest in applying LPS and Lean Construction in Yobe State has developed in the top management staff of the Ministry of Housing. It was concluded that effective training and implementation in the application of Lean Construction techniques will reduce waste and non-value-adding steps from planning and design through construction.This will increase value and reduce the exorbitant cost and time to deliver structures.